Point Mountain Solar
514 MW generation in Upton, TX · In queue since July 2022
514 MW
Capacity
1
Components
Solar
3y 10m
In Queue
—
IA Status
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Point Mountain Solar project is a proposed 514 MW solar generation facility located in Upton County, Texas. The development project is in the ERCOT interconnection queue as entry ERCOT-25INR0049, with a queue entry date of July 18, 2022. The project's status is currently listed as suspended.
The Point Mountain Solar project has been the subject of recent news coverage, with eight articles published across industry and regulatory news categories.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTop solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.