Three W Solar
110.89 MW generation in Hill, TX · In queue since March 2022 · Proposed COD May 2026
110.89 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Status
Signed Mar 2023
Queue → IA
1 year
IA → COD
3y 2m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-15
The Three W Solar project is a proposed 110.89 MW solar generation facility in Hill County, Texas. The project, developed by Three W Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0055. It entered the interconnection queue on March 7, 2022, with a proposed commercial operation date of May 15, 2026. The project's Interconnection Agreement (IA) was executed on March 28, 2023.
The Three W Solar project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Three W Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 3522 Hillboro1_8 - 237 Blanton CKT 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Three W Solar