Albatross BESS
50.4 MW storage in Mclennan, TX · In queue since May 2022 · Proposed COD February 2028
50.4 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-22
The Albatross BESS project is a proposed 50.4 MW battery storage project located in McLennan County, Texas. Developed by Albatross Solar, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0071 on May 16, 2022. The current proposed commercial operation date is February 22, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 50.4 MW of battery storage capacity. The point of interconnection is specified as "From Bus #165 Windsor Switch To Bus #161 McGregor". The Albatross BESS project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Albatross Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
From Bus #165 Windsor Switch To Bus #161 McGregor
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.