Violet Storage
151 MW storage in Nueces, TX · In queue since May 2022 · Proposed COD July 2029
151 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
Violet Storage is a proposed 151 MW battery storage project located in Nueces County, Texas. The project, developed by VIOLET STORAGE, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0076, with a queue entry date of May 10, 2022. The proposed commercial operation date is July 1, 2029, and its interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Violet Storage is the McKenzie Road (8858) 138 kV Substation. The project has been mentioned in recent news coverage related to the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
VIOLET STORAGE
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
McKenzie Road (8858) 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.