Reis Solar
105.48 MW generation in Atascosa, TX · In queue since June 2022 · Proposed COD August 2027
105.48 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-03
The Reis Solar project is a proposed 105.48 MW solar generation facility in Atascosa County, Texas. Developed by Greenalia Solar Power Reis LLC, the project consists of 105.48 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-25INR0082, with a queue entry date of June 2, 2022, and a proposed commercial operation date of August 3, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing Reis Solar Park operating plant (EIA ID 67564). Interconnection will be at a tap into the 138 kV line from Choke Canyon AEP to San Miguel Gen. The Reis Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Atascosa
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenalia Solar Power Reis LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping into 138 kV line (5689) Choke Canyon AEP to (5902) San Miguel Gen
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SAN_SANMIGG1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Reis Solar