Goldeneye BESS
201.6 MW storage in Bell, TX · In queue since June 2022 · Proposed COD May 2028
201.6 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed Feb 2024
Queue → IA
1y 8m
IA → COD
4y 3m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-05-15
The Goldeneye BESS project is a proposed 201.6 MW battery storage project located in Bell County, Texas. Developed by Black Mountain Energy Storage II, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0100 on June 10, 2022. The project's proposed commercial operation date is May 15, 2028.
The interconnection agreement for the Goldeneye BESS project has been executed as of February 26, 2024. The point of interconnection is the 3423 KILLEEN Switch 138 KV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3423 KILLEEN Switch 138 KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Goldeneye BESS