August Draw Energy (ERCOT-25INR0112) — Project Summary

Queue ID
ERCOT-25INR0112
Capacity
250 MW
Technology
Solar
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
DBR Solar, LLC
IA Status
Facility Study

August Draw Energy

ERCOT-25INR0112BetaActiveSolarERCOTLBNL + Live

250 MW generation in Reeves, TX · In queue since September 2022 · Proposed COD June 2028

250 MW

Capacity

1

Components

Solar

3y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 9m

Facilities Study50%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-27

About

August Draw Energy is a proposed 250 MW solar generation project located in Reeves County, Texas. Developed by DBR Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0112. The project entered the interconnection queue on September 15, 2022, and has a proposed commercial operation date of June 27, 2028. Its interconnection status is currently in the Facility Study phase.

The August Draw Energy project has been mentioned in recent news coverage related to industry and development.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Reeves

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

DBR Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 60207 Verhalen _x0013_ 60808 Hoefs Road

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about August Draw Energy