Sagewood BESS
100.57 MW storage in Glasscock, TX · In queue since September 2022 · Proposed COD March 2028
100.57 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
The Sagewood BESS project is a proposed 100.57 MW battery storage project located in Glasscock County, Texas. Developed by Sagewood BESS, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0142, with a queue entry date of September 21, 2022.
The proposed commercial operation date is March 31, 2028. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sagewood BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV McDonald Road Switch (bus #1333) _x0013_ Desert Wind Sub (bus #11282)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.