Blue Heron BESS
201.08 MW storage in Reeves, TX · In queue since October 2022 · Proposed COD March 2028
201.08 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
Blue Heron BESS is a proposed 201.08 MW battery storage project located in Reeves County, Texas. The project, developed by Blue Heron BESS, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0146. It entered the interconnection queue on October 24, 2022, and has a proposed commercial operation date of March 31, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 201.08 MW of battery storage capacity. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blue Heron BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV MANSON (1094) - Riverton (11083)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Blue Heron BESS