Holly Branch Storage (ERCOT-25INR0148) — Project Summary

Queue ID
ERCOT-25INR0148
Capacity
115.32 MW
Technology
Battery
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
Holly Branch Solar, LLC
IA Status
Facility Study

Holly Branch Storage

ERCOT-25INR0148BetaActiveBatteryERCOTLBNL

115.32 MW storage in Robertson, TX · In queue since June 2023 · Proposed COD June 2027

115.32 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

4 years

Facilities Study50%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

About

The Holly Branch Storage project is a proposed 115.32 MW battery energy storage system in Robertson County, Texas. Developed by Holly Branch Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0148, with a queue entry date of June 7, 2023. The proposed commercial operation date is June 1, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap 345kV 967 Gibbons Creek - 3400 Twin Oak. The project has appeared in recent news coverage regarding energy storage developments in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Robertson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Holly Branch Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 967 Gibbons Creek - 3400 Twin Oak

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Gibbons Creek Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Holly Branch Storage