Academy Wind
304.56 MW generation in Dickens, TX · In queue since September 2022
304.56 MW
Capacity
1
Components
Wind
3y 8m
In Queue
—
IA Status
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Academy Wind is a proposed 304.56 MW wind generation project located in Dickens County, Texas. The project, developed within the ERCOT region, entered the ERCOT interconnection queue as entry 25INR0151 on September 15, 2022. Its current status is listed as suspended.
The proposed project consists solely of wind generation with a total capacity of 304.56 MW. Academy Wind has been the subject of recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.