Nymphaea Storage
61 MW storage in Wichita, TX · In queue since September 2022 · Proposed COD July 2028
61 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Nymphaea Storage is a proposed 61 MW battery storage project located in Wichita County, Texas. The project, developed by Nymphaea Solar, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-25INR0155, with a queue entry date of September 21, 2022. Its proposed commercial operation date is July 1, 2028, and its interconnection status is currently in the Facility Study phase.
The point of interconnection for Nymphaea Storage is Tap 345kV 1730 Krum West Swtich - 6111 Riley7B.
Generated from interconnection queue and public data sources
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Nymphaea Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1730 Krum West Swtich - 6111 Riley7B
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Nymphaea Storage