Timberlakes Solar (ERCOT-25INR0165) — Project Summary

Queue ID
ERCOT-25INR0165
Capacity
203.5 MW
Technology
Solar
Status
active
Location
Dickens, TX
Region
ERCOT
Developer
Donegalsol
IA Status
Facility Study

Timberlakes Solar

ERCOT-25INR0165BetaActiveSolarERCOTLBNL + Live

203.5 MW generation in Dickens, TX · In queue since November 2022 · Proposed COD April 2028

203.5 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 5m

Facilities Study50%
Queue EntryNov 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

About

Timberlakes Solar is a proposed 203.5 MW solar generation project located in Dickens County, Texas. The project, developed by Donegalsol, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0165, with a queue entry date of November 7, 2022. Its proposed commercial operation date is April 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for Timberlakes Solar is the 59904 Cottonwood 345kV location. The project has appeared in recent news coverage regarding renewable energy development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Dickens

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Donegalsol

Utility

Entity

ERCOT

Service Type

Point of Interconnection

59904 Cottonwood 345kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Cottonwood Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.