Pinewood Solar
150.68 MW generation in Brazoria, TX · In queue since September 2022 · Proposed COD April 2028
150.68 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-14
Pinewood Solar is a proposed 150.68 MW solar generation project located in Brazoria County, Texas. The developer is Brazoria Solar II, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0170, with a queue entry date of September 2, 2022. The proposed commercial operation date is April 14, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 150.68 MW of solar photovoltaic generation. The point of interconnection is the 43020 Seabreeze 345kV substation. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brazoria Solar II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
43020 Seabreeze 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pinewood Solar