Wolf Spring Solar
195.7 MW generation in Dickens, TX · In queue since December 2022 · Proposed COD April 2028
195.7 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
1y 8m
IA → COD
3y 8m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-19
Wolf Spring Solar is a proposed 195.7 MW solar generation project located in Dickens County, Texas. The developer is Wolf Spring Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-25INR0172, with a queue entry date of December 7, 2022, and a proposed commercial operation date of April 19, 2028. The interconnection agreement for the project was executed on August 14, 2024.
The Wolf Spring Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wolf Spring Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Sub
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26