Concho Pearl Storage
162.4 MW storage in Concho, TX · In queue since December 2022 · Proposed COD October 2027
162.4 MW
Capacity
1
Components
Battery
3y 5m
In Queue
IA Executed
IA Status
Signed Jul 2024
Queue → IA
1y 7m
IA → COD
3y 3m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-10-14
The Concho Pearl Storage project is a proposed 162.4 MW battery energy storage system in Concho County, Texas. The project, developed by Concho Pearl Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0175. It entered the interconnection queue on December 15, 2022, with a proposed commercial operation date of October 14, 2027.
The project's Interconnection Agreement (IA) has been executed as of July 22, 2024. The point of interconnection (POI) is Tap 345kV 76009 Twin Buttes - 7077 Amos Creek. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Concho
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Concho Pearl Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76009 Twin Buttes - 7077 Amos Creek
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANG_ALL
- POI Substation
- Twin Buttes Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.