Triangle Ranch Charlie
200.22 MW generation in Cottle, TX · In queue since September 2022
200.22 MW
Capacity
1
Components
Wind
3y 8m
In Queue
—
IA Status
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Triangle Ranch Charlie is a proposed 200.22 MW wind generation project located in Cottle County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-25INR0179, with a queue entry date of September 15, 2022. Its status is currently listed as suspended.
The development project is composed entirely of wind generation, totaling the full 200.22 MW capacity. The developer is listed as ERCOT. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cottle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Triangle Ranch Charlie