Inadale Solar
281.03 MW generation in Scurry, TX · In queue since February 2023 · Proposed COD July 2028
281.03 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-25
Inadale Solar is a proposed solar generation project located in Scurry County, Texas. The project, with a total capacity of 281.03 MW, is being developed by Inadale Solar, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0196, with a queue entry date of February 20, 2023. The proposed commercial operation date is July 25, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Inadale Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Inadale Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV TONKAWAW_5 (11048) _x0013_ SCURCNTYS_5 (11318) Circuit #2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14