Veer Energy
90.72 MW generation in Reeves, TX · In queue since December 2022 · Proposed COD December 2026
90.72 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The Veer Energy project is a proposed 90.72 MW solar generation facility located in Reeves County, Texas. The project, developed by DBR Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0201, with a queue entry date of December 7, 2022.
The proposed commercial operation date for the Veer Energy project is December 31, 2026. Its interconnection status is currently in the Facility Study phase. The point of interconnection is TAP 69kV 38040 IH20 - 38090 Pecos.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
DBR Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 69kV 38040 IH20 - 38090 Pecos
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.