Shadow Ranch Solar
807.61 MW generation in Upton, TX · In queue since September 2022 · Proposed COD June 2026
807.61 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The Shadow Ranch Solar project is a proposed 807.61 MW solar generation facility in Upton County, Texas. The project, developed by LectricWind LLC, is located within the ERCOT region and interconnected to the 842 King Mountain 345kV point of interconnection. It entered the ERCOT interconnection queue as entry ERCOT-25INR0207 on September 27, 2022, and has a proposed commercial operation date of June 1, 2026. The project's interconnection status is currently in the Facility Study phase.
The Shadow Ranch Solar project has been featured in recent news coverage related to deals.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LectricWind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
842 King Mountain 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SPTX12B_RN
- POI Substation
- King Mountain Southwest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.