Burgos Solar
105.52 MW generation in Milam, TX · In queue since October 2022 · Proposed COD November 2027
105.52 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-22
The Burgos Solar project is a proposed 105.52 MW solar generation facility in Milam County, Texas. The project, developed by Twin Oaks Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0214, with a queue entry date of October 18, 2022. The proposed commercial operation date is November 22, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The Burgos Solar project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Twin Oaks Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3701 Rookie Switch 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.