Hector Storage
42.69 MW storage in Navarro, TX · In queue since October 2022 · Proposed COD December 2027
42.69 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Hector Storage project is a proposed 42.69 MW battery energy storage system in Navarro County, Texas. Developed by Hector Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0221, with a queue entry date of October 24, 2022. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Haney (213) - Hubbard_8 (3515) 138kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hector Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Haney (213) - Hubbard_8 (3515) 138kV Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hector Storage