Uhland Maxwell
188.4 MW generation in Caldwell, TX · In queue since September 2022 · Proposed COD August 2025
188.4 MW
Capacity
1
Components
Gas
3y 8m
In Queue
IA Executed
IA Status
Signed Mar 2023
Queue → IA
6 months
IA → COD
2y 5m
Total Duration
6 months
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-08-19
The Uhland Maxwell project is a proposed 188.4 MW gas-fired generation project located in Caldwell County, Texas. Developed by the Lower Colorado River Authority, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0223, with a queue entry date of September 27, 2022. The proposed commercial operation date is August 19, 2025, and the project's Interconnection Agreement (IA) was executed on March 3, 2023.
The point of interconnection (POI) for the Uhland Maxwell project is at Clear Springs (#7050) and L_Hornsb8_1Y (#7047). The project has been the subject of recent news coverage, with 12 articles published across industry, grid, and development categories.
Generated from interconnection queue and public data sources
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lower Colorado River Authority
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Clear Springs (#7050) and L_Hornsb8_1Y (#7047)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.