Apache Hill BESS
200.92 MW storage in Hood, TX · In queue since November 2022 · Proposed COD July 2026
200.92 MW
Capacity
1
Components
Battery
3y 6m
In Queue
IA Executed
IA Status
Signed Jun 2024
Queue → IA
1y 7m
IA → COD
2y 1m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-07-31
The Apache Hill BESS project is a proposed 200.92 MW battery storage project located in Hood County, Texas. It is being developed by Apache Hill Energy Center and is interconnected within the ERCOT region under queue ID ERCOT-25INR0231. The project entered the interconnection queue on November 7, 2022, with a proposed commercial operation date of July 31, 2026.
The project's Interconnection Agreement (IA) has been executed as of June 26, 2024. The Point of Interconnection (POI) is the 363 Hood 138kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Hood
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
APACHE HILL ENERGY CENTER
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
363 Hood 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.