Isaac Solar
50.54 MW generation in Matagorda, TX · In queue since November 2022 · Proposed COD December 2026
50.54 MW
Capacity
1
Components
Solar
3y 6m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
11 months
IA → COD
3y 2m
Total Duration
11 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
The Isaac Solar project is a proposed 50.54 MW solar generation facility located in Matagorda County, Texas. Developed by Industrial Bravo Project LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0232. The project entered the interconnection queue on November 7, 2022, with a proposed commercial operation date of December 31, 2026. An Interconnection Agreement (IA) was executed on October 18, 2023. The point of interconnection is the 8114 Conoco 138kV.
The proposed project is linked to the existing operating Isaac Solar facility (EIA plant ID 68380). Recent news coverage indicates interest in the project, with articles focusing on industry, regulatory, development, and grid-related aspects.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial Bravo Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8114 Conoco 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- POI Substation
- Wadsworth Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.