CLUTCH CITY STORAGE I SLF
16.63 MW storage in Galveston, TX
16.63 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed CLUTCH CITY STORAGE I SLF project is a 16.63 MW battery storage development in Galveston County, Texas. The project is located within the ERCOT region and consists entirely of battery storage.
The project is listed in the ERCOT interconnection queue as entry 25INR0243. Its status is currently suspended.
Generated from interconnection queue and public data sources
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CLUTCH CITY STORAGE I SLF