Strawberry Acres Storage (ERCOT-25INR0248) — Project Summary

Queue ID
ERCOT-25INR0248
Capacity
156.73 MW
Technology
Battery
Status
active
Location
Wilson, TX
Region
ERCOT
Developer
Strawberry Acres Energy Center, LLC
IA Status
Facility Study

Strawberry Acres Storage

ERCOT-25INR0248BetaActiveBatteryERCOTLBNL + Live

156.73 MW storage in Wilson, TX · In queue since November 2022 · Proposed COD September 2028

156.73 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 10m

Facilities Study50%
Queue EntryNov 23, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

About

Strawberry Acres Storage is a proposed 156.73 MW battery storage project located in Wilson County, Texas. The project, developed by Strawberry Acres Energy Center, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0248, with a queue entry date of November 23, 2022. The proposed commercial operation date is September 30, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 5132 Eagle Creek Substation 138kV. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wilson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Strawberry Acres Energy Center, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

5132 Eagle Creek Substation 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Eagle Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Strawberry Acres Storage