Strawberry Acres Storage
156.73 MW storage in Wilson, TX · In queue since November 2022 · Proposed COD September 2028
156.73 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Strawberry Acres Storage is a proposed 156.73 MW battery storage project located in Wilson County, Texas. The project, developed by Strawberry Acres Energy Center, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0248, with a queue entry date of November 23, 2022. The proposed commercial operation date is September 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 5132 Eagle Creek Substation 138kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Strawberry Acres Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5132 Eagle Creek Substation 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Eagle Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Strawberry Acres Storage