Nockenut Springs Solar 5
201.15 MW generation in Gonzales, TX · In queue since February 2023 · Proposed COD June 2029
201.15 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-05
The Nockenut Springs Solar 5 project is a proposed 201.15 MW solar generation facility in Gonzales County, Texas. The project, developed by Pecan Springs Energy, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0280, with a queue entry date of February 9, 2023. The proposed commercial operation date is June 5, 2029. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Tap 345 kV 5133 Elm Creek - 5915 South Texas Project.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecan Springs Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5133 Elm Creek - 5915 South Texas Project
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.