Cosper Solar
148.16 MW generation in Bell, TX · In queue since January 2023 · Proposed COD November 2027
148.16 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-12
The Cosper Solar project is a proposed 148.16 MW solar generation facility in Bell County, Texas. Developed by Gransolar Texas Twenty LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-25INR0281 on January 3, 2023. The proposed commercial operation date is November 12, 2027, and the project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Cosper Solar operating plant (EIA ID 67773).
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Twenty LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 115 Ding Dong - 3630 Copperas Cove Tu
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Ding Dong Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.