Hornet Solar II SLF
208.95 MW generation in Castro, TX · In queue since January 2023 · Proposed COD July 2028
208.95 MW
Capacity
1
Components
Solar
3y 4m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
1y 7m
IA → COD
3y 11m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-07-31
Hornet Solar II SLF is a proposed solar generation project with a total capacity of 208.95 MW. The project, developed by Hornet Solar II LLC, is located in Castro County, Texas, and is interconnected within the ERCOT region. It entered the ERCOT interconnection queue as project number ERCOT-25INR0282 on January 3, 2023, with a proposed commercial operation date of July 31, 2028.
The project's Interconnection Agreement (IA) has been executed as of August 21, 2024. The point of interconnection (POI) is the Ozark Trail Switch 345kV substation (Bus #23901). The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Castro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hornet Solar II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Ozark Trail Switch 345kV substation (Bus #23901)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Ozark Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.