RIVERBEND SOLAR SLF
301 MW generation in Falls, TX · In queue since March 2023 · Proposed COD December 2027
301 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Riverbend Solar SLF project is a proposed 301 MW solar generation facility in Falls County, Texas. The project, being developed by Riverbend Renewables, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0297, with a queue entry date of March 8, 2023. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the TAP 345 KV line between the Tradinghouse (#3405) and Temple Pecan Creek (#3412) substations. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Riverbend Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV LINE FROM TRADINGHOUSE (#3405) TO TEMPLE PECAN CREEK (#3412) SUBSTATIONS
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.