Northington Solar
129.81 MW generation in Wharton, TX · In queue since February 2023 · Proposed COD July 2027
129.81 MW
Capacity
1
Components
Solar
3y 3m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
1y 8m
IA → COD
2y 9m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-15
Northington Solar is a proposed solar generation project located in Wharton County, Texas, with a total capacity of 129.81 MW. The project is being developed by Northington Solar, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0319, with a queue entry date of February 20, 2023, and a proposed commercial operation date of July 15, 2027.
The project's Interconnection Agreement (IA) has been executed as of October 2, 2024. The point of interconnection (POI) is on the 138 kV El Campo (#8102) - Pulsar (#8192) Line, managed by AEP. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Northington Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
The 138 kV El Campo (#8102) - Pulsar (#8192) Line; AEP.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Northington Solar