Normangee Solar
120.68 MW generation in Leon, TX · In queue since March 2023 · Proposed COD June 2027
120.68 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
The Normangee Solar project is a proposed 120.68 MW solar generation facility in Leon County, Texas. The project, developed by Normangee Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0320, with a queue entry date of March 13, 2023. The proposed commercial operation date is June 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap 345kV 3391Jewett - 44645 Singleton. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Leon
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Normangee Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3391Jewett - 44645 Singleton
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Normangee Solar