Longbow BESS (ERCOT-25INR0328) — Project Summary

Queue ID
ERCOT-25INR0328
Capacity
180.8 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Longbow BESS, LLC
IA Status
IA Executed

Longbow BESS

ERCOT-25INR0328BetaActiveBatteryERCOTLBNL

180.8 MW storage in Brazoria, TX · In queue since January 2023 · Proposed COD January 2025

180.8 MW

Capacity

1

Components

Battery

3y 4m

In Queue

IA Executed

IA Status

Signed Jul 2023

Interconnection

Queue → IA

6 months

IA → COD

1y 6m

Total Duration

6 months

Schedule

16 months past proposed COD

Construction75%
Queue EntryJan 23, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 18, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-01-11

About

Longbow BESS is a proposed 180.8 MW battery storage project in Brazoria County, Texas. Developed by Longbow BESS, LLC, the project consists entirely of battery technology. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0328, with a queue entry date of January 23, 2023, and a proposed commercial operation date of January 11, 2025.

The project's Interconnection Agreement (IA) was executed on July 18, 2023. The point of interconnection is the 42875 Danbury 138kV. This development is linked to the existing Longbow BESS, LLC operating plant (EIA plant ID 67083). The Longbow BESS project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Longbow BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

42875 Danbury 138kV

Data Source

LBNL

DeveloperClean Capital PartnersPR Newswire · 2024-02-12
TransactionTax equityPR Newswire · 2024-02-12
Deal value$118.5MPR Newswire · 2024-02-12
OfftakerFoss & CompanyPR Newswire · 2024-02-12
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
LON_RN1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Longbow BESS