Project Lynx BESS
125.36 MW storage in Nueces, TX · In queue since March 2023 · Proposed COD May 2026
125.36 MW
Capacity
1
Components
Battery
3y 2m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
1y 1m
IA → COD
2y 1m
Total Duration
1y 1m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
Project Lynx BESS is a proposed 125.36 MW battery storage project located in Nueces County, Texas. The developer is Corpus Battery Storage, LLC. The project consists of a single 125.36 MW battery component.
The project is in the ERCOT interconnection queue as entry ERCOT-25INR0329, with a queue entry date of March 8, 2023, and a proposed commercial operation date of May 1, 2026. The interconnection agreement has been executed as of April 9, 2024. The point of interconnection is the 138KV Tap 8921 Terra Verde - 8518 Kingsville.
Generated from interconnection queue and public data sources
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Corpus Battery Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138KV Tap 8921 Terra Verde - 8518 Kingsville
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Lynx BESS