Clutch City Solar Phase II
251.27 MW generation in Brazoria, TX · In queue since February 2023 · Proposed COD July 2028
251.27 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Clutch City Solar Phase II is a proposed solar generation project located in Brazoria County, Texas, with a total capacity of 251.27 MW. The project, being developed by HZ SOLAR I, LLC, consists entirely of solar photovoltaic generation. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0330, with a queue entry date of February 20, 2023, and a proposed commercial operation date of July 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for Clutch City Solar Phase II is tap 138kV 42960 Mustang Bayou _x0013_ 42100 Hudson CKT#04. The project has appeared in recent news coverage regarding solar development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
HZ SOLAR I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 42960 Mustang Bayou _x0013_ 42100 Hudson CKT#04
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Clutch City Solar Phase II