Buffalo Meadow Solar
251.27 MW generation in Robertson, TX · In queue since February 2023 · Proposed COD September 2028
251.27 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
The Buffalo Meadow Solar project is a proposed 251.27 MW solar generation facility in Robertson County, Texas. Developed by Buffalo Meadow Energy Center, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0331, with a queue entry date of February 27, 2023. The proposed commercial operation date is September 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap Jack Creek (975) - Twin Oak (3400) 345kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Robertson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Buffalo Meadow Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Jack Creek (975) - Twin Oak (3400) 345kV line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Buffalo Meadow Solar