Jaguarundi Solar
90.29 MW generation in Archer, TX · In queue since March 2023 · Proposed COD July 2027
90.29 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The Jaguarundi Solar project is a proposed 90.29 MW solar generation facility in Archer County, Texas. The project, developed by Jaguarundi Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0335, with a queue entry date of March 27, 2023. The proposed commercial operation date is July 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the NAVY KICKAPOO SWITCH (NAVYKSS1_8 #1472). The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Archer
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Jaguarundi Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
NAVY KICKAPOO SWITCH (NAVYKSS1_8 #1472)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jaguarundi Solar