Butcherbird Solar
116 MW generation in Bell, TX · In queue since December 2023 · Proposed COD February 2027
116 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
Butcherbird Solar is a proposed 116 MW solar generation project located in Bell County, Texas. The project, developed by Butcherbird Solar, LLC, entered the ERCOT interconnection queue as queue ID ERCOT-25INR0337 on December 18, 2023. Its proposed commercial operation date is February 1, 2027, and its interconnection status is currently in the Facility Study phase.
The project consists of 116 MW of solar photovoltaic generation. The point of interconnection is Tap 138 kV - Bell County #133 to Bartlett Switch #114. The project is listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Butcherbird Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV - Bell County #133 to Bartlett Switch #114
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.