Butcherbird Solar (ERCOT-25INR0337) — Project Summary

Queue ID
ERCOT-25INR0337
Capacity
116 MW
Technology
Solar
Status
active
Location
Bell, TX
Region
ERCOT
Developer
Butcherbird Solar, LLC
IA Status
Facility Study

Butcherbird Solar

ERCOT-25INR0337BetaActiveSolarERCOTLBNL + Live

116 MW generation in Bell, TX · In queue since December 2023 · Proposed COD February 2027

116 MW

Capacity

1

Components

Solar

2y 5m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 2m

Facilities Study50%
Queue EntryDec 18, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-02-01

About

Butcherbird Solar is a proposed 116 MW solar generation project located in Bell County, Texas. The project, developed by Butcherbird Solar, LLC, entered the ERCOT interconnection queue as queue ID ERCOT-25INR0337 on December 18, 2023. Its proposed commercial operation date is February 1, 2027, and its interconnection status is currently in the Facility Study phase.

The project consists of 116 MW of solar photovoltaic generation. The point of interconnection is Tap 138 kV - Bell County #133 to Bartlett Switch #114. The project is listed as active in the ERCOT interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Bell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Butcherbird Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 kV - Bell County #133 to Bartlett Switch #114

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.