Echols Creek Solar
201.15 MW generation in Lamar, TX · In queue since April 2023 · Proposed COD April 2027
201.15 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-03
Echols Creek Solar is a proposed 201.15 MW solar generation project located in Lamar County, Texas. Developed by BT Ferguson Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0368. The project entered the interconnection queue on April 7, 2023, and has a proposed commercial operation date of April 3, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Echols Creek Solar operating plant (EIA plant ID 68902). Recent news coverage has highlighted the project, with articles appearing in the "deals" and "industry" categories.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Ferguson Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.