Echols Creek Storage
100.57 MW storage in Lamar, TX · In queue since April 2023 · Proposed COD December 2026
100.57 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The Echols Creek Storage project is a proposed 100.57 MW battery energy storage system in Lamar County, Texas. The project is being developed by BT Ferguson Solar, LLC and is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0369, with a queue entry date of April 7, 2023.
The proposed commercial operation date for the Echols Creek Storage project is December 31, 2026. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770).
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Ferguson Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW