Meridian BESS
31.23 MW storage in Bosque, TX · In queue since March 2023 · Proposed COD October 2027
31.23 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
The Meridian BESS project is a proposed 31.23 MW battery storage project located in Bosque County, Texas. Developed by Navitas Energy- Meredian BESS, the project consists entirely of battery storage.
The project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0374, with a queue entry date of March 13, 2023. The proposed commercial operation date is October 1, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Bosque
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Navitas Energy- Meredian BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
319 Meridian 69 KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Meridian Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.