Proteus Vernon Solar SLF
75 MW generation in Wilbarger, TX · In queue since March 2023 · Proposed COD February 2029
75 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-18
The Proteus Vernon Solar SLF project is a proposed 75 MW solar generation project located in Wilbarger County, Texas. The project is being developed by Vernon Solar and Storage LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-25INR0377, with a queue entry date of March 27, 2023, and a proposed commercial operation date of February 18, 2029. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 75 MW of solar photovoltaic generation. The point of interconnection is the 6060 Vernon 138kV substation. The Proteus Vernon Solar SLF project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vernon Solar and Storage LLC (a Delaware LLC)
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6060 Vernon 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Vernon Main Street Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Proteus Vernon Solar SLF