Fike BESS
200.8 MW storage in Hidalgo, TX · In queue since May 2023 · Proposed COD June 2027
200.8 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-18
The Fike BESS project is a proposed 200.8 MW battery storage project located in Hidalgo County, Texas. Developed by BRP Blue Topaz 9, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0380, with a queue entry date of May 15, 2023.
The proposed commercial operation date for the Fike BESS project is June 18, 2027. The project's interconnection status is currently in the Facility Study phase. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Blue Topaz 9, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5754 Aderhold 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Aderhold Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fike BESS