HappyDogSolar (ERCOT-25INR0382) — Project Summary

Queue ID
ERCOT-25INR0382
Capacity
85.54 MW
Technology
Solar
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Rosula Solar LLC
IA Status
IA Executed

HappyDogSolar

ERCOT-25INR0382BetaActiveSolarERCOTLBNL + Live

85.54 MW generation in Milam, TX · In queue since June 2023 · Proposed COD April 2027

85.54 MW

Capacity

1

Components

Solar

2y 11m

In Queue

IA Executed

IA Status

Signed Dec 2024

Interconnection

Queue → IA

1y 6m

IA → COD

2y 4m

Total Duration

1y 6m

Construction75%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 16, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-04-13

About

HappyDogSolar is a proposed solar generation project located in Milam County, Texas, with a total capacity of 85.54 MW. Developed by Rosula Solar LLC, the project entered the ERCOT interconnection queue as ERCOT-25INR0382 on June 7, 2023. The proposed commercial operation date is April 13, 2027.

The project's interconnection agreement (IA) was executed on December 16, 2024. The point of interconnection (POI) is Tap 345kV 3704 Hog Creek Switch _x0013_ 3687 Bell County East Switch. The project is currently listed as active in the ERCOT queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rosula Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 3704 Hog Creek Switch _x0013_ 3687 Bell County East Switch

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about HappyDogSolar