Macho Creek BESS (ERCOT-25INR0390) — Project Summary

Queue ID
ERCOT-25INR0390
Capacity
150.56 MW
Technology
Battery
Status
active
Location
Starr, TX
Region
ERCOT
Developer
Macho Creek BESS, LLC
IA Status
Facility Study

Macho Creek BESS

ERCOT-25INR0390BetaActiveBatteryERCOTLBNL + Live

150.56 MW storage in Starr, TX · In queue since June 2023 · Proposed COD May 2027

150.56 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

About

The Macho Creek BESS project is a proposed 150.56 MW battery storage project located in Starr County, Texas. Developed by Macho Creek BESS, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0390, with a queue entry date of June 28, 2023.

The proposed commercial operation date for the Macho Creek BESS project is May 31, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 8793 RIO GRANDE CITY - 8806 LAS LOMAS.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Starr

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Macho Creek BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 8793 RIO GRANDE CITY - 8806 LAS LOMAS

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
LV4_UNIT_1
POI Substation
Rio Grande City Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.