MICOT BESS
150 MW storage in Montgomery, TX · In queue since March 2023 · Proposed COD May 2025
150 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
2y 2m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-30
The MICOT BESS project is a proposed 150 MW battery storage project located in Montgomery County, Texas. Developed by UR-Silo DevCo LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0393, with a queue entry date of March 27, 2023.
The proposed commercial operation date for MICOT BESS is May 30, 2025. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 44645 Singleton - 46500 Tomball Ckt 74.
Generated from interconnection queue and public data sources
State
TX
County
Montgomery
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
UR-Silo DevCo LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 44645 Singleton - 46500 Tomball Ckt 74
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LMO_ESR_RN
- POI Substation
- Singleton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about MICOT BESS