Hinkell BESS
78.05 MW storage in La Salle, TX · In queue since August 2023 · Proposed COD July 2027
78.05 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The Hinkell BESS project is a proposed 78.05 MW battery storage project located in La Salle County, Texas. Developed by Reveille BESS, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0395. The project entered the interconnection queue on August 21, 2023, and has a proposed commercial operation date of July 1, 2027. Its interconnection agreement status is currently in the Facility Study phase.
The development project consists solely of battery storage, with a total capacity of 78.05 MW. The point of interconnection is the 8612 Reveille 138kV substation. The project is currently listed as active within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Reveille BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8612 Reveille 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Reveille Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hinkell BESS