WOE Gyp King Wind
315 MW generation in King, TX · In queue since April 2023 · Proposed COD August 2030
315 MW
Capacity
1
Components
Wind
3y 1m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-08-31
The WOE Gyp King Wind project is a proposed 315 MW wind generation project located in King County, Texas. Developed by White Oak Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0401, with a queue entry date of April 19, 2023. The proposed commercial operation date is August 31, 2030, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 315 MW of wind generation capacity. The point of interconnection is Tap 138kV 33798 GYP_18 _x0013_ 6088 BENJ4A. The WOE Gyp King Wind project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
King
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
White Oak Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 33798 GYP_18 _x0013_ 6088 BENJ4A
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.