Pledgor BESS
100.33 MW storage in Matagorda, TX · In queue since May 2023 · Proposed COD April 2028
100.33 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-06
The Pledgor BESS project is a proposed 100.33 MW battery storage project located in Matagorda County, Texas. The developer is listed as Pledgor BESS. It is an active project in the ERCOT interconnection queue (queue ID ERCOT-25INR0405), with a queue entry date of May 3, 2023, and a proposed commercial operation date of April 6, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The Pledgor BESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pledgor BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Gulftie (43340) _x0013_ Pledger (43120) circuit 60
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26